CIMB BANK BHD v. GAN
TEOW HOOI & ORS [2012] 9 CLJ 1003
COURT OF APPEAL,
PUTRAJAYA
ZAINUN ALI JCA, RAMLY
ALI JCA, KANG HWEE GEE JCA
[CIVIL APPEAL NO:
W-02(IM)(NCC)-2470-2010]
CONTRACT: Loan - Default of repayment of loan - Sale
and purchase of Land to build House - Construction Agreement - Execution of
loan Agreement - Investigation by Local Government and Housing Ministry on
project - Vendor/contractor did not possess licence as Housing developer -
Whether sale and purchase Agreement and construction Agreement void ab initio
The
respondents had entered into a sale and purchase agreement with Paragon Nova
Sdn Bhd ('the vendor') to purchase a vacant land at the price of RM125,000.
Concurrently, the respondents also entered into a construction agreement with
Atlaw Housing Sdn Bhd ('the contractor') to build a two and a half storey house
on the vacant land at the price of RM200,000 which was to be paid in accordance
with the third schedule of the construction agreement. The respondents applied
for a housing loan in the sum of RM280,000 and this was approved by the
appellant. The agreement stipulated that RM100,000 was to be released to the
vendor for the purchase of vacant land while RM180,000 was for the building or
construction price to the contractor. A loan agreement between the appellant
and the respondents was executed and the loan sum of RM 100,000 was released to
the vendor for the purchase of vacant land while the balance sum of RM180,000
was released to the contractor, pursuant to cl. 2 of the Third Schedule of the
construction agreement. Since there was no notice of completion of work sent to
the appellant, the sum of RM180,000 was not released to the contractor. The
respondents defaulted in the repayment of the loan as stipulated in an express
term of the loan agreement and several notices of demand were issued to the
respondents. Almost a year later, the respondents lodged a police report
against the vendor and contractor, on the basis that they did not have license
as housing developer. On 9 April 2008, the Local Government and Housing
Ministry issued a letter informing them they are in the process of investigating
the said project. The appellant subsequently sent a notice of demand claiming
for the total loan amount which was released to the respondents inclusive of
the accrued interest. However no payment was made by them. The appellant then
filed the writ of summons against the respondents. In the High Court, the main
issue raised by the appellant was whether the sale and purchase agreement and
construction agreement were void ab initio since the vendor/contractor
did not have licence as housing developer. The appellant's claim was dismissed
with costs. Hence, the present appeal against the said decision by the trial
judge.
Held (allowing appeal with costs)
Per Zainun Ali JCA delivering the judgment of the court:
(1) The learned trial judge had misdirected himself in
arriving at the decision he did. The said loan agreement was valid even if the
sale and purchase agreement and construction agreement was illegal and void.
Even if there was non-compliance with the Housing
Development (Control and Licensing) Act 1966 for failing to obtain the
required license as housing developer, it would not render the sale and
purchase agreement and or the construction agreement as null and void. (paras
24-25 & 33)
(2) The loan sum had been released at the respondents'
request and at all material times, there was no instruction from the respondent
borrowers to stop the progressive release of the loan. Relying on such
representation by the respondents, the appellant was under no duty to further
verify the legality of the sale and purchase agreement and construction
agreement. The principle of estopped applies. The respondents did not take
either of these courses of action, and as such, must be deemed to have affirmed
the legality of the agreements. In any case too, it would be unjust and
inequitable to allow the respondents to raise the issue of illegality after
seven of years the sale and purchase agreement and construction agreement
having been executed. (paras 27-28 & 35-36)
Case(s) referred to:
Legislation referred to:
Counsel:
For the appellant - Hizri
Hasshan (Ashmadi Othman & Mohd Helmy Razelan with him); M/s Che Mokhtar
& Ling
For the respondent - Teh Beng Boon (Soo Pei
Ping with him); M/s BB Teh
[Appeal from High Court, Kuala Lumpur; Suit
No: D-22-NCC-193-2009]
Reported by Najib Tamby
No comments:
Post a Comment